Littleton Bridge Replacements Taylor Street over Interstate 495

Littleton, MA
$36M
MassDOT
Bridge Construction

Project Overview

Project Overview:

This interchange reconstruction project included six (6) bridge replacements with median crossovers including one temporary Acrow bridge. SPS installed steel H Piles, concrete footings at abutments and piers; Installed steel superstructures and concrete bridge decks with parapets and safety features; Performed a full highway reconstruction from subgrade up; and completed full paving, and installation of highway lighting, drainage, guide signs and safety features.

Interesting Facts / Figures

SPS used accelerated operations to gain back one full year on the schedule that was lost due to fiber optic relocations.

Interesting Facts / Figures

SPS used accelerated operations to gain back one full year on the schedule that was lost due to fiber optic relocations.