In late August, the DWW-SPS JV implemented our Phase 1 Temporary Traffic Control Plan on I-195 in New Bedford. The traffic control plan shifted the two lanes of traffic on I-195 Eastbound and Westbound into the right shoulder, and temporary barrier was installed to provide a work zone in the median. The DWW SPS JV has spent the last two months reconstructing the median on I-195 to create a crossover that moves the two lanes of I-195 Westbound Traffic onto I-195 Eastbound. This crossover is anticipated to be completed in November, and demolition of the I-195 Westbound bridge will follow.
Additionally, the I-195 Eastbound Ramps to Route 18 were closed to vehicular traffic on September 8th. Demolition I-195 Eastbound Off Ramp to Route 18 SB is underway and nearly complete at this time.