During the MBTA‘s recent 10-day Green Line shutdown from August 2nd – August 11th, the Railroad-SPS JV completed various track and site improvements in Boston’s Allston neighborhood along Commonwealth Ave. Our work included over 2,200 feet of full depth track replacement, including more than 450 feet of grade crossing replacement at Warren Street and Allston Street. The JV also installed 1,600 feet of new track drainage pipe, replaced 2,000 feet of restraining rail, reset hundreds of granite curbs, installed 4 new duct banks to support MBTA traction power, and installed new asphalt platforms at Warren and Allston stations. This extensive work resulted in 8 speed restrictions being removed from the Green Line B Branch. The work was completed successfully with the help of our subcontractors and continuous support from the City of Boston and various MBTA departments.