District 6: Tunnel Systems Repair I-90 & 93
Boston - Central Artery Tunnel
$15,343,725.00
MassDOT
Structures Maintenance
Project Overview
Project Overview:
- Tunnel system leak sealing, fireproofing and miscellaneous repairs (including painting) along Interstates 90 & 93 (Ted Williams and Thomas P O’Neil Tunnels) and Route 1A (Sumner and Callahan Tunnels)
- Installation of temporary fireproofing and cover at ITT expansion joints.
- Replacement of prestressed concrete wall panels.
- Repair of overhead concrete repairs.
- Replacement of existing drainage and access structures in the roadway.
Key Challenges Overcome:
Limited working hours. Typically, 4 hours of work each night due to traffic restrictions.
Limited access to specific locations through coordination with MassDOT and other Contractors in the area.
Interesting Facts / Figures
SPS New England is currently servicing general repairs to the tunnel with 4 separate crews performing a variety of long term repairs and maintenance to keep the tunnel in working condition for generations to come.