Littleton Bridge Replacements Taylor Street over Interstate 495
Littleton, MA
$36M
MassDOT
Bridge Construction
Project Overview
Project Overview:
This interchange reconstruction project included six (6) bridge replacements with median crossovers including one temporary Acrow bridge. SPS installed steel H Piles, concrete footings at abutments and piers; Installed steel superstructures and concrete bridge decks with parapets and safety features; Performed a full highway reconstruction from subgrade up; and completed full paving, and installation of highway lighting, drainage, guide signs and safety features.
Interesting Facts / Figures
SPS used accelerated operations to gain back one full year on the schedule that was lost due to fiber optic relocations.
Interesting Facts / Figures
SPS used accelerated operations to gain back one full year on the schedule that was lost due to fiber optic relocations.