The Seabrook-Hampton Project Team was busy in May 2026 with finishing the substructure concrete, installing structural steel, hosting Safety Week, and much more. The final pier cap placement was completed to wrap up over 6,000 cy of concrete for all the substructure and 48 out of 78 steel girders have been installed as the superstructure starts to take shape.