The SPS-Walsh JV has been making progress at the Newton-Weston Project.

Construction of the three bridges that make up Ramp G, which carries traffic from I-95 to I-90 Eastbound, is now substantially complete. Traffic has been successfully shifted from the existing bridges and ramp to the newly constructed structures. Crews are now preparing for the demolition and removal of the existing bridges and ramp.

Crews have also completed bridge deck placements for this phase of construction on the I-90 mainline bridges. Work is now focused on installing the cast-in-place median barrier in preparation for shifting I-90 Westbound traffic onto the new bridge. This traffic switch will allow crews to demolish the existing westbound bridge and begin the final phase of construction.