The Bond Civil & Utility – SPS New England Joint Venture is excited to share this video recapping a major milestone at Logan International Airport.
In the fall, the Terminal C Roadways project at Logan International Airport for The Massachusetts Port Authority successfully demolished two structures, installed the final bridge span, and re-opened a new roadway to Terminal C, working around the clock in only nine days.
Thank you to our Joint Venture partners Bond Civil Construction all craft employees and subcontractors involved who performed their work safely and on schedule; and our subcontractors, notably Select Demo, Atlantic Bridge and Engineering, Baycrane, Brox Industries, and Markings, Inc.
A special thanks to Windwood Productions LLC for working with the Joint Venture to produce this video.
SPS is proud to announce the completion of another project for our valued client at MassDOT in Canton, along I-95 and Dedham St. This $50M project was years in the making and added a new off-ramp from I-95, replaced five bridges, upgraded public utilities, and improved a 1 Mile stretch of roadway.
This monumental task required crews to work seven days a week for months on end to meet the project completion date.
Congratulations and THANK YOU to all the dedicated SPS employees, subs and suppliers who worked together to deliver another Successful Project.
Special thanks to Phitted Media for producing this video.
SPS forces deployed within the Boston Common to perform repairs to the tunnel roof above the MBTA Boylston Station. The work included on-track shoring of the existing tunnel ceiling in coordination with the overhead power and catenary.
As part of the Green Line Surge project SPS headed up the effort to perform concrete repairs within the MBTA Copley Station.
Crews performed crack injection and leak sealing work along an inaccessible stretch of the isolated MBTA D-Branch and then the busy, confined historical downtown tunnel corridor. SPS continues to respond quickly to the call for transit infrastructure repairs.
SPS and Railroad Construction Company (RCC) crews completed over 2,000 feet of rail and tie replacement. In the station platform pit areas, the team completed concrete and rubber insert installations.
The Belden G. Bly Drawbridge Project achieved a significant milestone yesterday. The Team performed a successful test opening of the new bridge at around 6:00pm.
Work began on this project in January of 2021. The bascule span erection work was restricted to occur during a USCG Saugus River channel closure between 2/1/24 and 5/15/24. The SPS Team, MassDOT and our Subcontractor partners worked tirelessly to achieve this milestone.
Congratulations to the entire Team.
Special thanks to Savanna Media for producing this video.
On June 3, 2024, SPS New England attended the Mark H. Hasso Project Excellence and Scholarship Awards Program hosted by the Construction Management Association of America (CMAA) – New England Chapter.
At the event, the Joint Venture team of BOND Civil & Utility Construction / SPS New England received the award of Project of the Year for the L1332-C4 Terminal B-C Main Roadways Project at Boston Logan International Airport for the Massachusetts Port Authority. Members of the project team took time to present the project to peers during the event.
Thank you to our partners on the successful project, Bond Civil & Utility, Stantec, and Massachusetts Port Authority.
SPS recently completed high priority overhead concrete and pile repairs at the Bass River Bridge in Yarmouth. Tight access, tides, growing repairs, and an expedited repair schedule made this project a challenge for everyone involved. The project started in January and was completed a few days prior to the Fourth of July weekend. It took a huge effort from SPS Superintendents, Foreman, Labor, Operations, Marine Division and Project Management . Mark Rousseau (Site Superintendent) was supported by Joe Harvey, Joe Ford, Nick Terenzoni, Ben Terenzoni, Jimmy Zechello, John Desimone, Jason Williams, Jeremiah Connolly, Chris Pickford, and very determined crew. Congratulations to everyone who made this one a success.
The Massachusetts Bay Transit Authority announced that the Dorchester Avenue Bridge in Boston is under construction.
The bridge, which is located between Von Hillern and Kemp streets, was built in 1925 and rehabilitated in 1975. The steel bridge carries vehicles, pedestrians and bicyclists over the Red Line, the Commuter Rail Old Colony Lines and the Cabot Yard maintenance tracks.
Photo courtesy of MBTA Customer and Employee Experience Department
It is being replaced to protect its structural integrity and ensure reliable service.
Work began on the project in the summer of 2022. The budget for the project is $47,125,079 and is provided by federal formula funds and some MBTA matching funds, according to Lisa Battison, a spokesperson of the MBTA.
The lead contractor on the project is SPS New England of Salisbury, Mass., and Select Demo Services of Salem, N.H., is the demolition contractor.
“Dorchester Avenue over the MBTA Red Line, Cabot Yard Spur and Old Colony Main Line consists of replacement of the existing three-span highway bridge with a new, two-span precast reinforced concrete deck panel slab and cast in place closure pours, sidewalks and barriers, on weathering steel multi-girder superstructure,” according to SPS New England. “A new pile supported abutment will be constructed behind the existing reinforced concrete rigid frame south abutment of the south span, using drilled and driven pipe piles and a reinforced cast-in-place concrete cap.
“A new pile supported pier will be constructed between the existing granite block south abutment of the north span and the reinforced concrete rigid frame north abutment of the middle span, using drilled and driven pipe piles and a reinforced cast-in-place concrete cap,” SPS added. “The existing granite block north abutment of the north span will be reused, and a new precast reinforced concrete cap will be placed on top to support the new superstructure.”
To relocate the existing utilities from the existing Dorchester Avenue bridge, a prefabricated temporary utility bridge will be erected on a reinforced concrete foundation supported by drilled micropiles. Work also includes the rehabilitation of an existing 300-ft. long bin wall by installing soil nails and a reinforced concrete face.
ENR New England is excited to announce this year’s group of regional Best Project winners, with 19 projects awarded in 13 main categories.
In addition to the 2024 main category winners found in the list below, the Best Projects safety and sustainability awardees, which are juried by a separate group of safety and sustainability experts, will be announced next month in the ENR New England free e-newsletter. Finalists for this year’s ENR New England Project of the Year will also be announced soon.
Projects were evaluated on the ability of the project team to overcome challenges, safety, construction/design quality, and contribution to the industry and the community.
Project Category: Airport/Transit
Regional Award Level: Award of Merit
Project Name: Logan International Airport – Terminal B-C Roadways Program
Thank you to Laborers Local 976, Piledrivers and Divers Local 56, Iron Workers Local 7, Carpenters Local 349, and Operating Engineers Local 4 for their participation and attendance yesterday morning signing a partnership agreement with OSHA. The partnership agreement signifies this group’s commitment to a safe and healthful jobsite at the NH1A Over Hampton River Bridge Replacement Project.
Wayne Capolupo of SPS New England, right, was named a community champion during the annual Our Neighbors’ Table breakfast Tuesday at the Blue Ocean Event Center in Salisbury. Also named a community champion was former Daily News columnist Charlene Dolan. An estimated 250 people attended the food pantry’s fundraiser.