District 6 Maintenance Update: September 2025

SPS is milling and paving nightly with Brox Industries, Inc. in the central artery tunnel of Boston. The work window is typically 4 hours nightly and all of the milled Microsilica wearing surface is replaced with new pavement on a nightly basis. We’re expecting to have a few thousand tons of pavement installed by the end of this year. Men in safety vests watching paving happen. Men in safety vests watching paving happen. A truck paving the road.

Seabrook-Hampton Bridge Replacement: September 2025

Seabrook-Hampton, NH Bridge Replacement Update: In collaboration with our partners — NH Department of Transportation, HDR< HUB Foundation Co., Inc., Redimix Companies, and Independent Concrete Pumping Corp.,—we are nearing completion of the deep foundations for the future bridge structure. Construction crews have started work on the substructure concrete for the piers and last week, the first pier footing was successfully completed, with a total concrete volume of 700 cubic yards.

a side view of the Seabrook-Hampton Bridge Replacement Project An overview of the Seabrook-Hampton Bridge Replacement Project An overview of the Seabrook-Hampton Bridge Replacement Project An overview of the Seabrook-Hampton Bridge Replacement Project A close up of work happening on the Seabrook-Hampton Bridge Replacement Project

Green Line D-Branch: September Update

Coming back to where it all started, the Railroad-SPS JV recently completed a 9-day shutdown on the MBTA Green Line D-Branch in early September. Our crews worked day and night to finish full depth replacement of a #5 and a #6 crossover at Fenway Station, including an additional 200 feet of full depth track replacement outside the turnouts. During the surge, our team also installed 1,400 new timber ties, 2,600 feet of rail, shot 23 thermite welds, and tamped almost 10,000 feet of track structure.

In addition, this surge marked the beginning of our work with Fischbach & Moore Electrical Group to install the MBTA’s new GLTPS system across the Green Line. Their electricians installed 128 new anchor assemblies and around 22,000 ft of new power supply cable, all while working in coordination with the ongoing track repairs.

All work was completed thanks to continued support from the City of Boston, Town of Brookline, and various MBTA Departments.

A view of track replacement work in progress. Track replacement work in progress. Completed tracks after replacement work.

CMAA Award Given to SPS New England for Dedham St. I-95 Interchange Rehabilitation/Replacement of 5 Bridges in Canton-Norwood-Westwood

On June 4, 2025, SPS New England attended the Mark H. Hasso Project Excellence and Scholarship Awards Program hosted by CMAA New England.

At the event, the SPS New England team received an award for our Dedham St. I-95 Interchange Rehabilitation/Replacement of 5 Bridges in Canton-Norwood-Westwood, MA for MassDOT.

Congratulations to the entire project team and special thanks to our partners for their support in this successful project.

Video by Phitted Media

SPS hosts The Moles New England Students’ Day

On October 24, 2025, SPS hosted The Moles New England Students’ Day at the Newton-Weston Bridge Bundle. The day began at Wentworth Institute of Technology with opening remarks by Pat Rooney and John McNamara of The Moles, President Mike Thompson of Wentworth Institute of Technology, MassDOT Highway Administrator & Undersecretary of Transportation Jonathan Gulliver, SPS Sr. Vice President of Business Development and Alternative Delivery Timothy McLaughlin, and Project Executives Bill Czerepak and Justin Ponting of the SPS-Walsh JV. Students had the opportunity to walk the site and attend stations hosted by SPS, Walsh, MassDOT, Gill Engineering, TetraTech, GeoEngineers, GTR, GZA, and Hub Foundation. Topics included MSE walls, traffic control, cofferdams, pile driving, micropiles, MBTA superstructure replacement, and more. Students also attended a career fair at Wenworth Institute of Technology.

Video credit: Savanna Media NE

 

Southampton Rail Yard Facility Groundbreaking: November 2025

The Railroad Construction Company – SPS New England Joint Venture (RCC-SPS JV) is honored to help bring Amtrak vision to life through construction of the Southampton Rail Yard Facility, an 860 ft. long maintenance facility designed to support the new Airo trainsets with daily inspections, service and cleaning. This project is one of more than 20 rail yard upgrades planned to strengthen Amtrak’s operations and improve the customer and employee experience.

New Bedford I-95 and Route 18 Interchange Project Update: November 2025

In late August, the DWW-SPS JV implemented our Phase 1 Temporary Traffic Control Plan on I-195 in New Bedford. The traffic control plan shifted the two lanes of traffic on I-195 Eastbound and Westbound into the right shoulder, and temporary barrier was installed to provide a work zone in the median. The DWW SPS JV has spent the last two months reconstructing the median on I-195 to create a crossover that moves the two lanes of I-195 Westbound Traffic onto I-195 Eastbound. This crossover is anticipated to be completed in November, and demolition of the I-195 Westbound bridge will follow.

Additionally, the I-195 Eastbound Ramps to Route 18 were closed to vehicular traffic on September 8th. Demolition I-195 Eastbound Off Ramp to Route 18 SB is underway and nearly complete at this time.

Newton-Weston I-90/I-95 Interchange – Rapid Replacement Weekends

This summer, the SPS-Walsh JV Team at the Newton/Weston I-90/I-95 Bridge Bundle project successfully completed a rapid bridge replacement of the Mass Pike (I-90) over MBTA Railroad.

The rapid bridge replacement was completed over two (2) separate 55-hour weekend shutdowns which included reducing I-90 traffic down to one (1) single lane each direction and full closure of the MBTA Railroad.

The scope of work included complete demolition of existing bridge superstructure, backwall concrete repairs, installation of precast bridge units, placement of rapid-setting concrete batched by on-site volumetric mobile mix trucks, milling, and paving of roadway approaches.

Both weekend bridge replacements were completed ahead of schedule with early opening of I-90 to all travel lanes prior to the 5AM Monday morning rush hour and no impacts to the return of Commuter Rail service.

This video by Savanna Media documents the process and the planning that went into the two rapid replacement weekends.

Farm Avenue Bridge over I-95 Project Update: November 2025

SPS Maintenance crews began substructure concrete repairs this week at the Farm Avenue Bridge over I-95 in Peabody. This work is part of an ongoing multi-bridge preservation contract. The superstructure repairs were completed in 2025, and the substructure repairs are scheduled to continue into 2026, with final completion expected next year.