Newton-Weston Bridge Bundle Project Update: June 2026

Another milestone completed on the Newton-Weston Bridge Bundle project. The SPS-Walsh JV successfully finished the final concrete bridge deck placements for this phase of construction. Crews worked long hours over six nights to place a total of 1,342 cubic yards of concrete. Next up: cast-in-place bridge barrier, bridge joint installation, and paving, followed by shifting westbound traffic onto the new bridge structure.

default

Haverhill II Project Update: June 2026

Deep foundations are behind us, summer is here, and the first substructure concrete is officially underway.

Crews recently completed the first footing and columns for the new I-495 Southbound Bridge Pier, marking the transition from deep foundations below grade, to the structure that will soon rise above it.

These photos show the work progression of the first placement for the new bridge as the project team transitions out of deep foundations.

Seabrook-Hampton Project Update: May 2026

The Seabrook-Hampton Project Team was busy in May 2026 with finishing the substructure concrete, installing structural steel, hosting Safety Week, and much more. The final pier cap placement was completed to wrap up over 6,000 cy of concrete for all the substructure and 48 out of 78 steel girders have been installed as the superstructure starts to take shape.

Newton-Weston Bridge Bundle Project Update: May 2026

default

In May, the SPS-Walsh JV team placed over 900 CY of concrete, split between multiple bridge decks, bridge barrier, approach slabs, and moment slabs.

Later that month, they worked several overnight shifts, placing the concrete bridge deck for the new I-90 mainline bridge. This placement is one of the many required to complete the current phase of construction and represents a highly coordinated effort by a skilled and experienced team.

Route 79/Davol Street Corridor Improvements Project Wins the American Society of Highway Engineers (ASHE) New England Section Project of the Year

SPS is proud to have be part of the Route 79/Davol Street Corridor Improvements Project on the D.W. White Construction – SPS New England Joint Venture with HNTB. This project was recently named as the American Society of Highway Engineers (ASHE) New England Section Project of the Year in the projects over $100 million category.

This project de-elevated and removed the Route 79 expressway, which allowed for both more waterfront access and approximately 21 acres of new open space.

This project will finish ahead of schedule, and it features the reconstruction of one bridge, four retaining walls, 3,000 linear feet of box culvert, six new stormwater infiltration basins, two new outfalls to the Taunton River, six new and reconstructed traffic signals, 100 pedestrian curb ramps, removal of 115,000 CY of earth, relocation of thousands of feet of utilities, and four miles of shared-use paths.

Read more about the project on our project page or read more about the award here.

Seabrook-Hampton Project Update: February 2026

The Seabrook-Hampton project team has continued substructure construction through the winter, with work focused on the precast pier footing elements. All precast pier footings have been lowered into position and are currently in a dewatered condition. Crews will begin installing the permanent reinforcing steel and concrete for each pier footing, followed by construction of the column and the pier cap. Structural bridge steel erection is planned to begin for late winter/ early spring, followed by the concrete bridge deck construction.

Crews have also began constructing a temporary access trestle on the eastern side of the existing bridge. This temporary trestle will be utilized for the future demolition of the existing bridge.

SPS hosts The Moles New England Students’ Day

On October 24, 2025, SPS hosted The Moles New England Students’ Day at the Newton-Weston Bridge Bundle. The day began at Wentworth Institute of Technology with opening remarks by Pat Rooney and John McNamara of The Moles, President Mike Thompson of Wentworth Institute of Technology, MassDOT Highway Administrator & Undersecretary of Transportation Jonathan Gulliver, SPS Sr. Vice President of Business Development and Alternative Delivery Timothy McLaughlin, and Project Executives Bill Czerepak and Justin Ponting of the SPS-Walsh JV. Students had the opportunity to walk the site and attend stations hosted by SPS, Walsh, MassDOT, Gill Engineering, TetraTech, GeoEngineers, GTR, GZA, and Hub Foundation. Topics included MSE walls, traffic control, cofferdams, pile driving, micropiles, MBTA superstructure replacement, and more. Students also attended a career fair at Wenworth Institute of Technology.

Video credit: Savanna Media NE

 

Southampton Rail Yard Facility Groundbreaking: November 2025

The Railroad Construction Company – SPS New England Joint Venture (RCC-SPS JV) is honored to help bring Amtrak vision to life through construction of the Southampton Rail Yard Facility, an 860 ft. long maintenance facility designed to support the new Airo trainsets with daily inspections, service and cleaning. This project is one of more than 20 rail yard upgrades planned to strengthen Amtrak’s operations and improve the customer and employee experience.